The calendar is important to define the schedule available of a resource in a week, of a cost center or the whole plant; its main purpose is to allocate machine load.


...

Specific Concepts


...

How to Add a Schedule Exception

...

  • Access the routine via PCP module through Updates / Registers / Schedule Exceptions.
  • In the routine, a calendar is displayed with the days of each month.
  • Place cursor on desired day and add the exception.


Help_buttonImage ModifiedImportant:

·    To add the entire day as an exception, do not select the hours because those hours selected are considered worked.

·    When running the machine load, the registered exception day is not considered for allocation.


...

Procedures

To include schedules in calendar:

...

8. Check the data and confirm it.


...

See Also